Patch schedule
| Seq | Patch | Lines | Prod (km) | Turns (h:mm) | Roll in (h:mm) | Total (d hh:mm) | Cumulative (d hh:mm) | Starts / ends | Check | |
|---|---|---|---|---|---|---|---|---|---|---|
Background
An ocean-bottom node survey turns the streamer model inside out. The receivers no longer hang behind the vessel; they sit on the seabed, recording whatever the source vessel fires over them, for weeks at a time. What makes nodes expensive is not the listening; it is the inventory. A survey of hundreds of square kilometres needs tens of thousands of recording stations, so nobody buys that many: a finite patch of nodes is laid on the seabed, shot, recovered, and rolled forward until the outline is covered.
Patch geometry. The node grid is coarse (a few hundred metres between stations) because the receivers stay put and see long offsets in every direction. The source lines over them are much finer, and every one of them is pure production for the source vessel: no streamers to drag, so the turns are tighter and the racetrack skips shorter than a streamer vessel could ever manage. Inside a patch the vessel works a racetrack; between patches it transits while the node crew works.
The roll is where programmes are won or lost. While the source vessel shoots patch N, the node vessel recovers patch N−1 and relays it to patch N+1. Node ops only cost time when a patch takes longer to relay than to shoot; the tool compares your relay time against the mean patch cycle and warns when the source vessel would be left waiting. That comparison, not the raw transit distance, is what sizes the node inventory: each patch holds up to the node count shown in the statistics, plus spares.
From clean time to a real estimate. The clean duration assumes every minute is spent shooting or turning. Real weather, gun faults and node waits take their share, so the tool divides by an operational uptime, adds mobilisation, and shows the gross duration the programme should carry, or switches to the monthly weather model, where each calendar month of the programme is scaled by its own uptime, so a winter start costs what a winter costs. With a programme start date set, the patch schedule and its CSV carry real start and end dates per patch, and the time budget bar splits the vessel’s days between shooting, turns and rolls, and standby. Day rates for the source vessel and node ops turn that duration into the number a bid is built on.
Getting the outline in. Draw it straight on the map — click to place vertices, then double-click or click the first vertex again to close — paste coordinates, or load a shapefile or GeoJSON. Coordinates can be metres, feet, US survey feet, longitude/latitude degrees or UTM easting/northing; a UTM .prj is recognised automatically, and with auto-detect the numbers are usually enough to tell. An outline given in degrees or UTM places the survey on Earth, so the survey centre and the KML export fill themselves in.
Obstruction zones. Platforms, islands, reef parks and exclusion zones do not move for the survey. Load them as a second file (same formats as the outline, same coordinate system), set a stand-off buffer, and every source line is clipped at the boundary of the zone plus the buffer: shorter lines, lettered splits, and pieces below the shortest-line-kept threshold dropped, with timing, node counts and KML all inheriting the holes. Node patches are not clipped: nodes record from wherever they sit, so a patch rectangle may overlap a zone; check the layout against local regulations before committing it.
Taking it with you. The plan exports as a KML that opens in Google Earth: outline, patch boundaries, node spots, every source line and every turn and roll coloured by status. It also exports as a zipped shapefile: source lines, node spots, patch outlines, the outline and any obstruction zones as separate shapefiles, in the coordinate system the outline came in, ready for QGIS or ArcGIS. The patch schedule exports as CSV for spreadsheets and acquisition schedules, and Print report produces a one-page plan view with the parameters, statistics and full schedule on it.
Assumptions and limits
- Second-azimuth pass. With it enabled, every patch is shot at the line azimuth plus the offset (90° by default) while the same nodes are deployed, so the node count and relay are unchanged and both passes appear in the schedule. The second pass uses the same line spacing, offset, shortest-line and obstruction rules, and its lines are clipped to each patch rectangle; the outline is not re-tiled for it. Line changes between the two passes are timed with the same turn model as any other change.
- Node relay runs in parallel with shooting and is modelled as the fixed relay time you set, compared against the mean patch cycle. If relay is slower, the tool warns but does not add the waiting time to the duration, so gross figures are then optimistic.
- Downtime is either a single uniform percentage or, with the monthly weather model, a per-calendar-month uptime walked from the programme start date, and each month dilates the clean time by its own factor. Real weather still comes in windows: treat the gross duration as a central estimate, not a promise. The regional presets are typical planning figures, not a metocean study.
- Turns, transits and patch rolls are all sailed at one speed. Real vessels slow into turns, so change times here are slightly optimistic.
- Nodes are laid on the bounding rectangle of each patch, which can extend past a ragged outline edge; nodes outside the boundary still record useful long-offset data, so this is usually conservative rather than wrong.
- Obstruction zones clip the source lines only. Turns, transits and rolls are still timed as straight-and-Dubins paths and are not routed around a zone, and node patches are laid out as if the zone were not there, so check the plan against the hazards before committing it.
- Every obstruction ring is treated as a solid keep-out, holes included; a polyline zone is closed with a straight chord between its ends.
- KML positions are converted from the local grid with a spherical-earth approximation around the survey centre, accurate to a few metres over typical survey sizes, not a geodesy replacement.
- The shapefile export is a zip of simple single-part shapefiles: geometry plus a few attributes, no symbology. It is meant for round-tripping the plan into a GIS, not as a finished map product; polygons are exported as closed rings in the outline’s own coordinate system.
The outline you load is parsed on this page and never uploaded; like every tool here, the file works offline, which is where survey planning tends to happen anyway.